Overview of the owner: Wuhu Oasis Environmental Protection and energy Co., Ltd., zheneng Jinjiang Group garbage power plant

Project time: January 2025

Project content: new Lide cb3-3.43/ 1.75/ 1

Replace NAC c6-3.43/0.98

Scope of work: construction drawing design, old unit removal, new unit design, manufacturing, installation, commissioning, civil engineering transformation, pipeline transformation, instrument control system transformation, generator recycling, electrical system transformation.

Duration: less than 6 months from project startup to grid connection