Scan and follow wechat official account
Case
|
Zhejiang Zhongdong Hengyuan
Owner profile: Zhejiang Zhongdong Hengyuan thermal power, Hangzhou Xiaoshan, cogeneration Project time: February 2025 Project content: new Lide b12-4.9/ 1.6/ 0.9 Replace NAC c12-4.9/0.98 Scope of work: demolition of old units, design, manufacture, installation, commissioning, civil engineering transformation and pipeline transformation of new units. Generator and electrical system reuse; Duration plan: Before shutdown: synchronous preparation of exhaust pipe / main pipe; After shutdown: dismantling, civil engineering and pipeline installation shall be carried out simultaneously; Installation: synchronous installation during the curing period of cast-in-place foundation; Manufacturing: the new unit is manufactured synchronously with the progress on site; Duration: 35 days (including Spring Festival) |