Zhejiang Zhongdong Hengyuan

image.png

Owner profile: Zhejiang Zhongdong Hengyuan thermal power, Hangzhou Xiaoshan, cogeneration

Project time: February 2025

Project content: new Lide b12-4.9/ 1.6/ 0.9

Replace NAC c12-4.9/0.98

Scope of work: demolition of old units, design, manufacture, installation, commissioning, civil engineering transformation and pipeline transformation of new units. Generator and electrical system reuse;

Duration plan:

Before shutdown: synchronous preparation of exhaust pipe / main pipe;

After shutdown: dismantling, civil engineering and pipeline installation shall be carried out simultaneously;

Installation: synchronous installation during the curing period of cast-in-place foundation;

Manufacturing: the new unit is manufactured synchronously with the progress on site;

Duration: 35 days (including Spring Festival)