Shaoxing yuandong thermal power
Owner profile: Shaoxing Far East thermal power, Binhai Industrial Zone, cogeneration Project time: 2014 Spring Festival Project content: new Lide b30-4.9/0.981 Replace NAC c25-4.9/0.981 Scope of work: demolition of old units, design, manufacture, installation of new units Commissioning, civil engineering transformation and pipeline transformation. Duration plan: Before shutdown: column construction, exhaust pipe / main pipe installation preparation; After shutdown: dismantling, civil engineering and pipeline installation shall be carried out simultaneously; Installation: synchronous installation during the curing period of cast-in-place foundation; Manufacturing: trial assembly of new unit before delivery Duration: 45 days, time + benefit Project promotion: Bosheng thermal power, Tianma thermal power, Hengyang thermal power, etc |