Shaoxing Far East thermal power

image.png

User name: Shaoxing Far East thermal power

Project location: Shaoxing, Zhejiang

Project background: upgrading high temperature and ultra high pressure boilers and steam turbine generator units

Operation date: 2019-2024

Model: B30-4.9/0.98、B12-11.2/3.0、B30-11.2/0.9、B20-11.2/3.1、B30-12.9/0.9、B15-13/0.9、B30-11.2/0.9

Dragging equipment: generator

Application: thermoelectricity, printing and dyeing

Features: high temperature and ultra-high pressure, multi-stage steam parameters; Large and continuous heat supply - high requirements for unit stability; Utilization of existing turbine room space;